Hi
The sprint cumulative flow and sprint burndown report work on different metrics. The cumulative flow will report the last day revisions of estimated effort aggregated of the sprint backlog items. Ideally this shouldn’t change once the sprint backlog task has been created. The burndown report will report last day revisions of work remaining aggregated of the sprint backlog items.
One reason why the report might have different starting point is because at the end of the first day of the sprint some of the sprint backlog tasks work remaining might have been readjusted to be higher than the estimated effort because of some impediments occurring or tasks which were under estimated?