Sprint Backlog item estimate
Hi

We had just completed our 3rd daily scrum of our frist Sprint. Everyone seems to be excited, as this is our first project using the Scrum process. During our daily scrum today it is discovered that a task which was estimated effort of 7 horus is now going to take 14 hours. I can't seems to be able to record that on the Sprint Backlog item form. How is the Scrum for Team system is recording this progress?
   Report 
   10-03-2008, 11:45 PM
Crispin Parker is not online. Last active: 11/13/2008 8:15:53 PM Crispin Parker

Top 10 Posts
Joined on 11-13-2007
Posts 664
Re: Sprint Backlog item estimate
Hi Joe,

This is a fairly common suituation in a scrum project. The "Work Remaining" should be adjusted to show the correct figure. The increase in the work reaming will show up as rise in the the Burn Down chart. However, the Scrum for Team System template doesn't provide a why to store information on errors in estimation of this sort.

Regards,

Crispin Parker,
Technical Consultant,
Conchango.

"It is better to light a candle than to curse the darkness"