Fractional Hours on Work Remaining in Reports
|
|
|
|
|
We've started using fractional hours in the work remaining field of SBIs, especially when the status is set to Ready for Test. The Sprint View report only shows whole hours. So, if an SBI has only 0.5 hours left for testing, the report shows 0. I can't say if this affects other reports, but is this something that can be fixed?
|
|
|
|
|
Report
|
|
|
|
10-03-2008, 11:35 PM
|
Crispin Parker
Joined on 11-13-2007
Posts 664
|
Re: Fractional Hours on Work Remaining in Reports
|
|
|
|
|
Hi,
I'll pass this on to our SQL Reports guru. Thanks for pointing it out.
Regards,
Crispin Parker, Technical Consultant, Conchango.
"It is better to light a candle than to curse the darkness"
|
|
|
|
|
Report
|
|
|
|
10-07-2008, 3:28 PM
|
Steve Wright
Joined on 02-05-2008
Egham
Posts 72
|
Re: Fractional Hours on Work Remaining in Reports
|
|
|
|
|
Hi aspears
Thank you for highlighting this defect. There are also a few other reports which have the same issue (Product Burndown Chart By Day, Sprint Burndown Chart and Sprint View).
This is caused by an incorrectly defined temporary table. One of the columns has been defined as an integer instead of a float. This has now been corrected and in the next release of the product.
Regards
Steve Wright Technical Consultant Conchango
|
|
|
|
|