Scrum for Team System - v2.x Discussions
Started by Crispin Parker at 03-11-2009 5:45 . Topic has 16 replies.
 
 
|
|
Sort Posts:
|
|
|
|
03-11-2009, 5:45
|
Crispin Parker
Joined on 11-13-2007
Posts 951
|
Re: PBI and SBI Work Remaining Synchronization Problem
|
|
|
|
|
Hi Joe,
Glad you finally got to the bottom of your configuration issue. The work item type name should be "Product Backlog Item". Nowhere in our template is the work item name ever spelt with an upper case "L".
I have only ever seen a problem like this once before when the Bug work item "Ready For Test" state ended up with a lower case "F". In that occurance it turned out that another Team Project had a work item with a "Ready for Test" state and the lower case "F" was being picked up from there. Team project work item templates should be completly seperate from one another inside TFS, however, it seems that this is not always the case.
Crispin.
"It is better to light a candle than to curse the darkness"
|
|
|
|
|
Report
|
|
|
|
02-04-2010, 2:18
|
kirlian
Joined on 02-03-2010
Brazil
Posts 1
|
Re: PBI and SBI Work Remaining Synchronization Problem
|
|
|
|
|
I installed the scrumforteamsystem recently at work, but unfortunately the PBI Work Remaining is not being updated.
The windows service is running, but when I access the webservice WorkItemChangedEndpoint.asmx, the following error appears: Could not load type 'Microsoft.TeamFoundation.WebAccess.CompressionModule'.
please someone could help me with this issue?
|
|
|
|
|
Report
|
|
|
|
|
|
Page 2 of 2 (17 items)
|
< 1 2 |
|
|
|
Scrum for Team ... » Version 2.x - T... » Scrum for Team ... » PBI and SBI Work Remaining Synchronization Problem
|
|
|
|